Introduction:
Ore conveying system in lanshan port south section, the main process equipment adopts advanced environmental protection of the tubular belt conveyor, design transport capacity of 20 million tons, hour capacity can reach 5500 tons, is currently the largest haul and comprehensive ability in Asia of the tubular belt conveyor system, is "rizhao city ten huimin projects", and "municipal key environmental protection engineerings.
Ore conveying system from working in the south, lanshan port meanders northward to rizhao steel loading bays
About 8.06 km of pipe machine ore conveying system about 11 km.
Design transport capacity of 20 million tons, transmission efficiency can reach 5500 tons/hour.
Tube machine system is composed of four transfer tower and three Pipe Belt Conveyor

C2A Pipe Belt Conveyor from the port area T1 transport: tower to T2 tower, driven by four drives, arrangement for "in the first three tail a" motor power is 1150 kw, each with a total installed power of 4 x 1150 kw, with a speed of 5 meters per second, pipe diameter is 500 mm。
C2A Pipe Belt Conveyor about 3 kilometers, passing through the yellow sea grain and oil Duan Quanjing photos

C3A pipe Belt Conveyor, drive device of motor driven by four sets of arrangement for the first three tail "a" motor power is 1150 kw, each with a total installed power of 4 x 1150 kw, with a speed of 5 meters per second, 500 mm in diameter, about 3.6 km, column top 21 meters, truss maximum span 65 meters.

C4A Pipe Belt Conveyor is about 1.4 km, from T3 towers across the coastal highway, the phoenix river, along the order of the phoenix river into rizhao steel mills, in ore conveying task at the same time, also form a beautiful coastal scenery line.

The system has been put into operation in August 2013, is currently operating normally, welcome all levels of users to visit, investigate and guide.